Hi
When we are updating the task start date of a particular task the below message is poping up in Project Professional and when we trying to update in Pwa and saving it automatically the save is becoming undone.
We are logging in with that user credentials and checking where the user has not charged any actuals on that task.
Then a message pops up saying:
- "The actual work in "xxxx" is out of sync with the actual work updated from timesheets. Actual work can only be updated by team members through PWA. Changes you have made to users' actual work will be lost during the save."
Can any body throw some light on the above issue.
Thanks
Geeth If you feel that the answer which i gave you is Helpful please select it as Answer/helpful.