Milestone %Complete - Don't want 0%, want % complete of the tasks it links to.

$
0
0

Hi - I have my project plan split into sections, one being milestones / deliverables and the other tasks. I want my milestones to show the start and end date of the tasks relevant to that piece of work and I have done that. So I have the following

1 Milestone: Write Document

2 Start of work

3 End of work

So row 2 links to the first task and row 3 links to the last task and 2 and 3 are children of 1, so brill. My problem is I also want the %complete. I know that the row I want which has the % complete in it is what row 2 is linked to, but I can't get that info to row 1. I was thinking that I could use a customer field but I don't see how that would work.

Any ideas?