What happen when I mark a task completed?

$
0
0

Hi

I configure the timesheet and tasksheet in project server 2010 using "Single Entry" mode. But, when I mark a task as a completed one, the project server automatically modifies all the actual values in my timesheet, exactly the same as the "Planned values" in all days.

But, I want a situation that I complete the task exactly in its current status, say, consider the following scenario:

  • Task Initial Planned work: 12 hours
  • Task Current Actual work: 8 hours
  • Task Actual work after "Mark as completed": 12 hours (The default config in project server)
  • Task Actual work after "Mark as Completed": 8 hours (My Case)

How can I implement this scenario using PSI? 