Project 2010 WCF Services - UpdateStatus Method in Statusing Service

$
0
0

Hi

I am using the Statusing.UpdateStatus(ChangeXML)method to Update Timephased data on assignment by day.

In Project 2010 you can specify the ResIDin the ChangeXML, which work 100% for normal Resources.

If I try to send updates through for a Cost Resource I get the following Error "AssignmentUidInvalid".

My requirement is to Update Actual Costs Time phased on a Cost Resource that is assigned to a Task in MSP.

Is there a way in the PSI to update this programmatically, or am I missing something?

I see that there is a list of valid fields that you can update with the Statusing.UpdateStatus(ChangeXML)method, but I don’t see any Cost Fields there so I assume that I cant update Actual Costswith this method?

http://msdn.microsoft.com/en-us/library/bb428845

Another Requirement that I have is to update the Budget Cost Field Time Phased onTask 0 where a Budget Resource is assigned.

Is it possible to Update Task0Time phase fields with the PSI? If So what WCF Service should I use? Or am I missing something?

Please also see screenshots:

It is Possible to Edit Cost for Cost Resources in MSP Time Phase on the assignment:

It is possible to Edit Budget Cost Time Phase on Budget Resource in MSP on the assignment: